Caldicot Skatepark Development – Monlife

Caldicot Skatepark Development

Maverick Skateparks has been working with Monmouthshire County Council to design an exciting new skatepark shaped by the people who will use it. Through engagement with local riders, skatepark users and the wider community, feedback has directly influenced the final layout, ensuring the facility reflects local needs while providing an inclusive space for all ages, abilities and wheeled sports disciplines.

The design combines a balanced mix of street and transition features, including a dedicated bowl and a welcoming street area connected to the main entrance. This space has been intentionally designed to support younger and less experienced riders as they build confidence, while carefully zoned areas allow beginners, families and experienced users to enjoy the facility safely and simultaneously. Generous spacing between features improves flow and safety, while interconnected zones create opportunities for more advanced riders to enjoy longer lines and transfers.

More than just a skatepark, this project will create a vibrant community space that encourages participation, supports healthy and active lifestyles, and brings people together. By placing local people at the heart of the design process, the finished facility will be a space that the community can be proud to call its own.


Latest updates

On target: 10/11/2026

Work has started on the new Caldicot Skatepark, part of an investment of around £500,000 in outdoor facilities at Caldicot Leisure Centre. Initial works including drainage has begun, with Maverick scheduled to begin initial skatepark construction during the week commencing 16th November.

The facility is on target to be completed by February 2027.

Shaped by feedback from skatepark users and the wider community, the design includes:

  • A dedicated bowl and a mix of street and transition features.
  • A beginner-friendly area where younger and less experienced riders can build confidence.
  • Seating, pathways, flood lighting and landscaping for riders, families and spectators.

The new facility will provide a welcoming space for different ages, abilities and wheeled sports—somewhere to learn, progress and enjoy being active together.


Key Dates

DateProject update
30 April 2026Skatepark survey closed.
By 27 July 2026Detailed designs to be shared with the community, subject to finalisation with Maverick.
Summer 2026Existing skatepark remains open during the summer school holidays.
Late September 2026Site works expected to begin.
13th October 2026Contractors will begin preparing the site from 13th October, allowing construction works to start as soon as final approvals are received. 
Early 2027The exciting new skate park remains on schedule for completion in February 2027. 

FAQs

We are continuing to progress plans for the redevelopment of Caldicot Skate Park. Below are some frequently asked questions to help keep residents and users updated as the project moves forward.

We are currently finalising the designs with Maverick and the Skate Park Committee. We hope to be able to share the updated designs by the end of the month.

No. The existing skate park will remain open during the summer school holidays.

Contractors will begin preparing the site from 13th October, allowing construction works to start as soon as final approvals are received. 

The exciting new skate park remains on schedule for completion in February 2027. 

 

The works are expected to take approximately 12 weeks to complete. Subject to progress and any unforeseen circumstances, the new facility is expected to open in early 2027.